Capital Works in Progress

Our 2025/26 Capital Works

In its capital works program, Council has planned expenditure of $31.9 million for 2025/26 including a total budget of about $8.3 million for major projects.

Importantly, Council is fully funding its renewal demand in transport, stormwater and property assets – to ensure that the level of service provided to the community by our roads, footpaths, drainage, community buildings and recreation facilities is maintained.

Capital projects for 2025/26 include:

  • Resurfacing of up to 7km of roads (2% of network);
  • Replacing up to 4 km of footpaths  (1% of network);
  • Main Road Footpath Renewal (Gavitt to Windsor)
  • Abbotsfield Road Footpath Improvement
  • Stage 2 of Renfrew Circle Reconstruction (Allardyce to Barron);
  • Albert Road Resurfacing
  • Giblins Reserve Playground Car Park Extension
  • Main Road Granton Shared Path Extension
  • Black Spot Projects in Sunmont Street, Chapel Street and Fourth Avenue
  • Vulnerable Road User Projects in Main Road Austins Fery and Central Avenue
  • Commence the project to repair and reopen the Glenorchy War Memorial Pool
  • International Food Garden
  • Humphreys Rivulet Rehabilitation
  • Playspace renewal at Apex Park (Lutana)
  • Public toilet replacement at Poimena Reserve
  • Replacement of various picnic shelters, seating, tables and BBQs
  • Abbotsfield Park cricket wickets
  • Abbotsfield Park lighting replacement
  • Redlands Drive Flood Mitigation (sedimentation basin)
  • Riverview Parade Stormwater Extension
  • Catherine Street Reserve Channel Restoration
  • Littlejohn Creek Flood Mitigation (105 Grove Road)

Where are the Planned Works Happening?

We perform ongoing works all year round as part of scheduled maintenance, capital works and operational management of Council’s assets.

To view a map of Council’s assets and planned Capital works, click the link below and select the layer ‘Capital Works’

Scheduled works are subject to change due to weather and other circumstances. If you have any enquiries please contact Council.

Stormwater Works

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Black Snake Road – drainage upgradeTue 30/6/26Tue 30/6/260%
Riverview Parade – stormwater extensionFri 29/8/25Mon 24/11/250%
Catherine Street Reserve – channel restoration (stage 1)Mon 5/05/25Tue 27/05/250%
Barclay Crescent and Apollo RoadTue 25/11/25Tue 9/12/250%
Abbotsfield Road and Hanlon Street – storm diversionsTue 30/6/26Tue 30/6/260%
Redlands Drive – flood mitigation worksMon 30/6/25Mon 29/9/250%
21 Sunshine Road – stormwater upgradeWed 10/12/25Tue 13/1/260%
Little John Creek – flood mitigationWed 14/1/26Mon 16/2/260%
Chapel Street Reserve – southern DN300 Replacement – stage 1Tue 17/2/26Wed 11/3/260%
Hamel Street – pipe repair and bank rehabilitationThu 12/3/26Wed 1/4/260%
Bowen Road – reliningTue 1/07/25Tue 1/07/250%
Richards Road – roadside drainage improvementThu 2/4/26Mon 27/4/260%
Kalang Avenue – roadside drainage improvementTue 28/4/26Wed 10/6/260%
New Town Rivulet RemediationTue 30/6/26Tue 30/6/260%

Road Resurfacing

Reseal ProgramEstimated Start DateEstimated Finish DatePercentage Complete
Cadbury Road – from Box Hill Road to Bilton StreetMon 3/11/25Tue 4/11/250%
Main Road – from Johnston Street to Lampton AvenueWed 5/11/25Thu 6/11/250%
Main Road – from Lampton Avenue to Windsor StreetFri 7/11/25Mon 10/11/250%
Main Road – from 247 Main Road to 255 Main RoadTue 11/11/25Tue 11/11/250%
Main Road – from Pascoe Avenue to Box Hill RoadWed 12/11/25Wed 12/11/250%
Car Park – outside Berriedale Tennis ClubThu 13/11/25Thu 13/11/250%
Brent Street – from Tolosa Street to Chapel StreetMon 17/11/25Tue 18/11/250%
Garden Grove – from Twelfth Street to Ashgrove GroveWed 19/11/25Wed 19/11/250%
Florence Street – from Main Road to Charles StreetThu 20/11/25Thu 20/11/250%
Derwent Park Road – from Brooker Highway to O’Grady AvenueFri 21/11/25Fri 21/11/250%
Derwent Park Road – from O’Grady to Cox AvenueMon 24/11/25Mon 24/11/250%
Derwent Park Road – from Cox Avenue to Bowen RoadTue 25/11/25Wed 26/11/250%
Springfield Avenue – from 42 Springfield Avenue to Coleman StreetThu 27/11/25Thu 27/11/250%
Springfield Avenue – from Homer Avenue to First AvenueMon 1/12/25Mon 1/12/250%
Berriedale Road – from Main Road to Chardonnay DriveTue 2/12/25Tue 2/12/250%
Marys Hope Road – from Katoomba Crescent to Riverview ParadeWed 3/12/25Wed 3/12/250%
Main Road – from Aurora Pole 362 to Aurora Pole 372Thu 4/12/25Fri 5/12/250%
Vehicular Right of Way – from Rocklyn Avenue to Albert RoadMon 8/12/25Mon 8/12/250%
Vehicular Right of Way – from Florence Street to Rocklyn AvenueTue 9/12/25Tue 9/12/250%
Devines Road – from Barossa Road to Loftus StreetWed 10/12/25Thu 11/12/250%
Jackson Street – from Albion Street to end of the roadMon 15/12/25Tue 16/12/250%
Jackson Street – from Chapel Street to Albion StreetWed 17/12/25Wed 17/12/250%
Sixth Avenue – from Easton Avenue to Twelfth AvenueThu 18/12/25Thu 18/12/250%
Sixth Avenue – from Eighth Avenue to Easton AvenueFri 19/12/25Fri 19/12/250%
Central Avenue – from Derwent Park Road to the end of the RoadMon 2/2/26Mon 2/2/260%
Easton Avenue – from Caversham Road to Sixth AvenueTue 3/2/26Tue 3/2/260%
Galston Road – from Huntley Street to Sussex StreetWed 4/2/26Wed 4/2/260%
Tenth Avenue – from Sixth Avenue to Easton AvenueThu 5/2/26Thu 5/2/260%
Walker Street – from Katoomba Crescent to Katoomba CrescentTue 10/2/26Tue 10/2/260%
Fleet Street – from Main Road to Sunderland StreetWed 11/2/26Wed 11/2/260%
Ebden Street – from Russell Road to 22 Ebden StreetThu 12/2/26Thu 12/2/260%
Lady Clark Avenue – from Main Road to 4 Lady Clark AvenueMon 16/2/26Mon 16/2/260%
Nathan Street – from Chandos Drive to 8 Nathan StreetTue 17/2/26Tue 17/2/260%
Montrose Road – from 124 Montrose Road to Nielson DriveWed 18/2/26Tue 24/2/260%
Albert Road – from Station Street to Gatehouse StreetWed 25/2/26Wed 25/2/260%
Albert Road – from Gatehouse Street to Central AvenueThu 26/2/26Fri 27/2/260%
**Click the button above to see map locations of these works**

Bridge Renewal

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
New Town Rivulet – walkway undermining repairMon 1/9/25Tue 30/9/250%
Islet Rivulet – abutment repointingMon 30/6/25Fri 4/7/25100%
GASP Walkway Bridge Corrosion Protection WorksMon 16/2/26Wed 11/3/260%
**Click the button above to see map locations of these works**

Footpath Renewal

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Main Road (from Gavitt Street to Windsor Street) footpath replacementMon 3/11/25Wed 15/4/260%
Abbotsfield RoadMon 1/09/25Thu 18/12/250%
Left footpath on Kilpa Street – Allunga Road to Junee StreetMon 21/7/25Mon 28/8/250%
Right footpath on Kilpa Street – Allunga Road to Junee StreetMon 26/8/25Fri 26/09/250%
Left footpath on Howard Road – Dodds Avenue to Gepp ParadeMon 29/9/25Mon 30/9/250%
Right footpath on Howard Road – Dodds Avenue to Gepp ParadeWed 1/10/25Tue 28/10/250%
Left footpath on Howard Road – Gepp Parade to House no. 96Wed 29/10/25Fri 21/11/250%
Left footpath on Howard Road – House no. 96 to Havelock AvenueMon 24/11/25Fri 2/1/260%
Left footpath on Grove Road – Anfield Street to Penguin DriveMon 7/7/25Fri 2/1/260%
Left footpath on Grove Road – Roseville Place to Main RoadTue 22/7/25Tue 5/8/250%
Right footpath on Grove Road – Roseville Place to Main RoadWed 6/8/25Mon 1/9/250%
Right footpath on Grove Road – Anfield Street to Penguin DriveMon 2/9/25 Wed 1/10/250%
Left footpath on Grove Road – Penguin Drive to Roseville PlaceTue 2/10/25Tue 7/10/250%
Right footpath on Grove Road – Penguin Drive to Roseville PlaceWed 8/10/25Wed 15/10/250%
Left footpath on Aldridge Court – Chatterton Court to House no. 16Mon 30/6/25Friday 4/7/2580%
Right footpath on Lampton Avenue – Howard Road to Brooker HighwayMon 5/1/26Tue 27/1/260%
Left footpath on Lampton Avenue – Howard Road to Brooker HighwayWed 28/1/26Tue 26/2/260%
Left footpath on Tamboon Road – Moondah Drive to Jimbirn StreetMon 11/8/25Fri 26/9/25100%
Footpath at Glenorchy Recreation GroundMon 29/9/25Mon 6/10/250%
Footpath from First Bowls Green to the corner boundary of Glenview HomeTue 7/10/25Thu 30/10/250%
Right footpath on Hamel Street – to the end of the roadFri 31/10/25Mon 1/12/25100%
Right footpath on Adelphi Road – Abbotsfield Road to Esdaile StreetTue 2/12/25Tue 9/12/250%
Left footpath on Adelphi Road – Abbotsfield Road to Esdaile StreetWed 10/12/25Wed 24/12/250%
Right footpath on Brent Street – Chapel Street to Anthony PlaceMon 30/6/25Fri 4/7/2580%
Left footpath on Brent Street – Chapel Street to Anthony PlaceMon 30/6/25Fri 4/7/25100%
Left footpath on Gormanston Road – Clifford Street to Derwent Park RoadFri 27/2/26Wed 18/3/260%
Right footpath on Gormanston Road – Clifford Street to Derwent Park RoadThu 19/3/26Wed 29/4/260%
Right footpath on Windsor Street – Main Road to Bowden StreetTue 9/12/25Tue 6/1/260%
Left footpath on Windsor Street – Main Road to Bowden StreetWed 7/1/26Tue 10/3/260%
Left footpath on Easton Avenue – Caversham Road to Sixth AvenueWed 11/3/26Wed 25/3/260%
**Click the button above to see map locations of these works**

New Footpath and Cycleway Construction

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Main Road Granton – shared path – Stage 2AMon 20/10/25Fri 19/12/250%
Main Road – Sealed Shoulder for CyclistsMon 5/1/26Fri 10/4/260%
**Click the button above to see map locations of these works**

Pavement Rehabilitation

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Cammeray Road – from Bradfield Street to Spring Street – (Stage 1)Tue 27/5/25Thu 28/08/250%
Renfrew Circle Road – reconstruction and traffic improvement – (Stage 2)Fri 10/10/25Wed 27/5/2760%
Florence Street – from Charles Street to Kelvin AvenueFri 19/12/25Mon 30/3/3/260%
Albert Road – from Main Road to Station StreetThu 5/3/25Thu 9/4/250%
Box Hill Road – from Centenary Crescent to Box Hill Road (Stage 1)Mon 10/11/25Mon 24/11/250%
Howard Road Parking Lane Reconstruction (Bunnings)Mon 2/2/26Mon 4/3/260%
Collinsvale Road – from Aurora Pole 15 to Stone CulvertMon 5/1/26Wed 4/2/260%
Molesworth Road Upgrade – Stage 1Thu 5/2/26Tue 14/4/260%
**Click the button above to see map locations of these works**

Road User Safety Improvement

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Access Project 1 – Central Avenue to Garden Road kerb Mon 14/7/25Mon 28/7/250%
Main Road – safety barrier and footpathMon 12/1/26Thu 12/2/260%
Grove Road Rail CrossingMon 25/8/25Mon 15/9/250%
Canberra Road – guard rail worksTue 29/7/25Tue 12/8/250%
Knights Point Reserve – car parkMon 16/3/26Thu 16/4/260%
Summont Street – safety barrierMon 2/3/25Wed 1/4/260%
Chapel Street – safety barrierThu 2/4/26Tue 21/4/260%
Fourth Avenue – high friction sealMon 8/12/25Mon 22/12/250%
Giblins Reserve Playground – car park extensionMon 3/11/25Wed 17/12/250%
**Click the button above to see map locations of these works**