Works in progress

We perform ongoing works all year round as part of scheduled maintenance, capital works and operational management of Council’s assets. Scheduled works are subject to change due to weather and other circumstances. If you have any enquiries please contact Council.

stormwater

Stormwater upgrade – Russell Road, Claremont

13 July 2021 - 20 August 2021

Works include installation of a new stormwater main and pits along the northern side of the roadway. Reduced speed limits and traffic management will apply. Small delays are expected during the day. Please follow signage or traffic controllers direction passing the work site.

Hours of Disruption: 7.00am - 4.30pm

Disruption Type: Stormwater upgrade

Footpath

Burton Street – Barossa Road intersection upgrade

28 June 2021 - 31 August 2021

Works include construction of two pram ramps and two kerb islands, installation of stormwater drain, kerb and channel, road re-seal and new line marking. Reduced speed limits apply please follow signage in place.

Hours of Disruption: 7.00am - 5.30pm

Disruption Type: Intersection upgrade

projects

Moonah CBD public toilets upgrade

26 April 2021 - 14 August 2021

The public toilets located in the Hopkins Street car park will be demolished and rebuilt. During construction reduced parking spaces and changes to traffic flow will be in place. This project is due to be completed in early August, subject to conditions. For any enquiries please contact the Property department at Council.

Hours of Disruption: 7.30.am - 5.30pm

Disruption Type: Facility upgrade

Footpath

Lutana Woodlands pathway renewal

22 March 2021 - 31 August 2021

Works include construction of a new entrance from Bowen Road, upgrade and realignment of internal pathways to provide better access for park users. Works will commence on 22nd March and planned for completion at the end of August, weather permitting. Access to some internal pathways will be restricted during construction works and please follow the signage on site. Council has engaged Kelly Civil Contracting Pty Ltd to complete the work.

Hours of Disruption: 7.00am - 5.00pm

Disruption Type: Pathway works

Road

Main Road, Glenorchy (Regina St to Barry St) – northbound lane only

11 January 2021 - 31 October 2021

As part of the CBD Revitalisation project final stage of works the northbound lane on Main Road, Glenorchy between Regina St and Barry St will be closed. Intersection works on Regina St are complete with traffic able to turn onto Regina St from Main Road. Traffic will not be able to access Main Road from Regina St as this remains a no-thru lane. The Glenorchy Bus Interchange remains open to public vehicles during works. The Southbound lane of Main Road is completely open. Pedestrian access remains open.

Hours of Disruption: 7.30.am - 5.30pm

Disruption Type: Road Closure